• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    004-25

  • Subject:

    Roads & Neighbourhood Services 2024/25 Carriageway and Footway Resurfacing Programme – Quarter 3 Progress Update

  • Responsible Officer:

    Thomas McMenamin, Executive Officer – Roads & Neighbourhood Services

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

  • The purpose of the Technical Note is to provide Elected Members with an update on the 2024/25 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme, following the completion of the second quarter of the financial year.
  • The Technical Note highlights the work programmes associated with internal and external resources, as well as providing an indication to when this work is programmed to be
  • In addition, the information also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from
  • All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
  • The Service will provide a final quarterly progress update via Technical Notes in March 2025.
  • The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
  • It should be noted that the programme and sequence of some locations have been altered from the previously issued Technical Note. This has been due to other works on the network impacting either directly on the planned location or the nominated diversion route. The team have attempted to substitute the locations and re-sequence the programme to ensure that the locations are caught later in the year.
  • Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
  • The undernoted information shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Milngavie

  • Dumgoyne Avenue (Phase 2)

Internal resources

Q1

April 2024

 

  • Ellangowan Road

Internal resources

Q2

August 2024

 

  • Mugdock Road /Ellangowan Road – RB included

Internal resources

Q2

August 2024

 

  • Keystone Quadrant

Internal resources

Q2

August 2024

 

  • Drumlin Drive

Internal resources

Q2

Postponed - Positive Coal Tar Test

 

  • Campsie Drive

Internal resources

Q3

October 2024

 

  • McGrigor Road

Internal resources

Q3

November 2024

 

  • Tambowie Crescent

Internal resources

Q3

December 2024

 

  • Allander Road

Internal resources

Q4

Bearsden North

  • Baljaffray Road (phase 3)

Internal resources

Q1

April 2024

 

  • Stockiemuir Road

Internal resources

Q1

April 2024

 

  • Russell Drive (phase 1)

Internal resources

Q1

June 2024

 

  • Russell Drive (phase 2)

Internal resources

Q1

June 2024

 

  • Milngavie Road (Phase 3) – BP Garage to Manse Road

Internal resources

Q3 

October 2024

 

  • Bailie Drive

Internal resources

Q3

October 2024

 

  • Campsie Drive

Internal resources

Q4

 

Bearsden South

  • Kessington Road (phase 2)

Internal resources

Q1

May 2024

 

  • Afton Crescent

Internal resources

Q1

May 2024

 

  • Boclair Road (phase 1)

Internal resources

Q1

June 2024

 

  • Boclair Road (phase 2)

Internal resources

Q2

July 2024

 

  • Ledi Drive

Internal resources

Q2

August 2024 - Brought forward from 2025-26 programme.

 

  • Methven Avenue + Kenmore Gardens + Ardoch Road

Internal resources

Q3

November 2024

 

  • Second Avenue

Internal resources

Q4

 

  • Rannoch Drive (phase 2)

Internal resources

Q4

 

  • Albert Drive

Internal resources

Q4

 

Bishopbriggs North & Campsie

  • Juniper Drive

Internal resources

Q3

October 2024

 

  • Forth Road/Queensview - Torrance

Internal resources

Q3

December 2024

 

  • Craigmarloch Avenue -Torrance

Internal resources

Q3

Postponed due to resource issues - Some patching work done-will reschedule into 3 years program 

 

  • Old Balmore Road

Internal resources

Q4

 

  • Campsie Road, Lennoxtown

Internal resources

Q4

 

Bishopbriggs South

  • Springfield Square

Internal resources

Q1

May 2024

 

  • Fintry Crescent and Tinto Road

Internal resources

Q1

June 2024

 

  • Wester Cleddens Road

Internal resources

Q1

June 2024

 

  • Crowhill Road (phase 1)

Internal resources

Q2

September 2024

 

  • Crowhill Road (phase 2)

Internal resources

Q2

September 2024

 

  • Angus Avenue

Internal resources

Q2

July 2024 Brought forward to July 2024 - Switch with Milngavie Road due to conflict with Canniesburn Toll

 

  • Elspeth Gardens

Internal resources

Q3

December 2024

 

Lenzie & Kirkintilloch South

  • Boghead Road (phase 2)

Internal resources

Q2

July 2024

 

  • Kirkintilloch Road, Lenzie (phase 1)

Internal resources

Q2

September 2024

 

  • Southbank Road

Internal resources

Q4

 

  • Douglas Gardens; Place; Court; and Avenue

Internal resources

Q4

 

  • Heather Gardens; Heather Place; and Forest Gardens

Internal resources

Q4

 

  • Heather Drive, Heather Place

Internal resources

Q4

 

Kirkintilloch East & North Twechar

  • Waterside Road (Phase 2-overlay)

Internal resources

Q1

April 2024

 

  • Oxford Street

Internal resources

Q1

May 2024

 

  • Kilsyth Road (phase 1)

Internal resources

Q1

June 2024

 

  • Main Street (phase 1), Twechar

Internal resources

Q2

Postponed to 2025-26 - Replaced with Ledi Drive - due to conflict with new outdoor center in Twechar

 

  • Main Street (phase 2), Twechar

Internal resources

Q2

Postponed to 2025-26 – Replaced with Ledi Dr- due to conflict with new outdoor center in Twechar

 

  • Applecross Road

Internal resources

Q3

November 2024

 

  • Braehead Street

Internal resources

Q3

November 2024

The undernoted information shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Milngavie
 

  • Main Street (Kelvin Timber to Waitrose)

Internal resources

Q1

June 2024

 

  • Mugdock Road

Internal resources

Q1

June 2024

 

  • Station Road

Internal resources

Q2

August 2024

 

  • Prestonfield

Internal resources

Q2

August 2024

 

Bearsden North

  • Milngavie Road (Westside near Mosshead Road)

Between Kelvin Timber and Waitrose

Q1

Duplicate -This section is called Main St, and it has already resurfaced in May 2024

 

  • Grampian Way

Internal resources

Q3

November 2024

 

Bearsden South

  • Crarae Avenue

Internal resources

Q1

May 2024

 

  • Westfield Drive

Internal resources

Q1

May 2024

 

  • Maxwell Avenue

Internal resources

Q1

June 2024

 

  • Drymen Road

Internal resources

Q2

Postponed Subject to Canniesburn Toll completion

 

  • Killermont Road

Internal resources

TBC

TBC Possibly required to carry out with an external resource - cross over from 2023-24- Councilor’s list

Bishopbriggs North & Campsie

  • Wester Cleddens Road

Internal resources

Q4

 

  • Teviot Avenue

Internal resources

TBC Coal Tar found- External contractor instructed to carry work in 2024-25

 

  • Allander Gardens

Internal resources

TBC Possible /required to carry out with an external resource- Cross over from 2023-24- Councilor’s list

 

Lenzie & Kirkintilloch South

  • Kirkintilloch Road, Lenzie

Internal resources

Q2

July 2024

 

  • Craigenbay Road

Internal resources

Q3

Postponed due to resource issues - Moved to 2025/26

 

  • Laxton Drive

Internal resources

Q3

December 2024

 

  • Bramley Place

Internal resources

Q3

December 2024

 

  • Glenwood Road and Place

Internal resources

Q3

September 2024

The undernoted information shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Milngavie
 

  • Clober Road

External resources

Q2

August 2024 - External contractor appointed to carry work in 2024-25

 

  • Blackwood Road

External resources

Q2

August 2024 - External contractor appointed to carry work in 2024-25

 

  • Dougalston Road

External resources

Q2

September 2024 - External contractor appointed to carry work in 2024-25

 

  • Connell Crescent

External resources

Q2

September 2024 - External contractor appointed to carry work in 2024-25

 

Bishopbriggs South

  • Brora Road & Crescent

External resources

Q2

September 2024 - External contractor appointed to carry work in 2024-25

 

  • Coltpark Avenue

External resources

Q3

December 2024 - External contractor appointed to carry work in 2024-25

 

  • Gannochy Drive

External resources

Q3

December 2024 - External contractor appointed to carry work in 2024-25

 

Bishopbriggs North & Campsie

  • Teviot Avenue

External resources

Q4 - External contractor appointed to carry work in 2024-25

 

Lenzie & Kirkintilloch South

  • Lithgow Avenue

External resource

Q4 - External contractor appointed to carry work in 2024-25

 

  • Gallowhill Avenue

External resource

Q2

August 2024 - External contractor appointed to carry work in 2024-25

The undernoted information shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Bishopbriggs South

  • Coltpark Ave

External resources

Q3

December 2024 - External contractor appointed to carry work in 2024-25

 

Bishopbriggs North & Campsie

  • Meadowburn

External resources

Q3

October 2024 - External contractor appointed to carry work in 2024-25

The undernoted information shows the locations selected as part of capital carriageway resurfacing 2023 /24. Regrettably, these locations were not progressed as part of the 2023/24 programme due the identification of coal tar. The works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations require full tendering exercise and framework. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Bearsden South

  • Durness Avenue (phase 1)

External resources

Completed March 2024 - Full length resurfaced

 

Bearsden North

  • Lawers Drive

External resources

TBC

TBC

 

Bishopbriggs South

  • Gannochy Drive

External resources

TBC

TBC - External contractor appointed to carry work in 2024-25

 

  • Rannoch Gardens

External resources

TBC

TBC - External contractor appointed to carry work in 2024-25

 

  • Lochy Gardens

External resources

TBC

TBC - External contractor appointed to carry work in 2024-25

 

  • Maree Gardens

External resources

TBC

TBC - External contractor appointed to carry work in 2024-25

 

  • Ness Gardens

External resources

TBC

TBC - External contractor appointed to carry work in 2024-25

The undernoted information shows the locations selected as part of capital footway resurfacing 2023-24. Regrettably, these locations were not progressed as part of the 2023/24 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations are required fully tendering exercise and framework. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.

Milngavie

  • South Mains Road

TBC

TBC

TBC - Investigation required for minor project based on desk top survey – subject to availability of budget

 

  • Kelvin Road

External resources

TBC

TBC

 

  • Crossburn Avenue

External resources

TBC

TBC

The Service has appointed an external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the pre-start meetings, the dates will be confirmed for sections 10, 11, 12, and 13.

In summary, the Service is commencing the year with the aspiration to complete the 63 carriageway and 25 footway locations listed but will add others if additional external resources can be secured during the financial year.