• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    076-24

  • Subject:

    Roads & Neighbourhood Services 2024/25 Carriageway and Footway Resurfacing Programme

  • Responsible Officer:

    Thomas McMenamin, Executive Officer – Roads & Neighbourhood Services

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

Section

  1. The purpose of the Technical Note is to provide Members with an overview of the 2024/25 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme.
  2. The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
  3. In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
  4. All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
  5. The Service will provide a further quarterly progress update via Technical Notes in July 2024, October 2024, and January 2025 along with a final update in March 2025.
  6. The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
  7. Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
  8. The under noted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.

Council Ward

Carriageway Resurfacing 2024/25

Quarter

Date Completed

Milngavie

 

 

 

 

Dumgoyne Avenue (Phase 2)

Internal resources

1

 

Ellangowan Road

Internal resources

2

 

Mugdock Road /Ellangowan Road –

RB included

Internal resources

2

 

Keystone Quadrant

Internal resources

2

 

Drumlin Drive

Internal resources

2

 

Campsie Drive

Internal resources

3

 

McGrigor Road

Internal resources

3

 

Tambowie Crescent

Internal resources

3

 

Allander Road

Internal resources

4

 

Bearsden North

 

 

 

Baljaffray Road (phase 3)

Internal resources

1

April 2024

Stockiemuir Road

Internal resources

1

April 2024

Russell Drive (phase 1)

Internal resources

1

 

Russell Drive (phase 2)

Internal resources

1

 

Milngavie Road (Phase 3) –

BP Garage to Manse Road

Internal resources

2 (subject to completion of Canniesburn Toll Project)

 

Bailie Drive

Internal resources

3

 

Campsie Drive

Internal resources

3

 

Bearsden South

 

 

 

Kessington Road (phase 2)

Internal resources

1

 

Afton Crescent

Internal resources

1

 

Boclair Road (phase1)

Internal resources

2

 

Boclair Road (phase2)

Internal resources

2

 

Methven Avenue + Kenmore Gardens + Ardoch Road

Internal resources

3

 

Second Avenue

Internal resources

4

 

Rannoch Drive (phase 2)

Internal resources

4

 

Albert Drive

Internal resources

4

 

Bishopbriggs North & Campsie

 

 

 

Juniper Drive

Internal resources

3

 

Forth Road/Queensview -Torrance

Internal resources

3

 

Craigmarloch Avenue -Torrance

Internal resources

3

 

Old Balmore Road

Internal resources

4

 

Campsie Road,            Lennoxtown

Internal resources

4

 

Bishopbriggs South

 

 

 

 

Springfield Square

Internal resources

1

 

Fintry Crescent and Tinto Road

Internal resources

1

 

Wester Cleddens Road

Internal resources

1

 

Crowhill Road (phase 1)

Internal resources

2

 

Crowhill Road (phase 2)

Internal resources

2

 

Angus Avenue

Internal resources

3

 

Elspeth Gardens

Internal resources

3

 

Lenzie & Kirkintilloch South

 

 

 

Boghead Road (phase 2)

Internal resources

2

 

Kirkintilloch Road, Lenzie phase 1

Internal resources

2

 

Southbank Road

Internal resources

4

 

Douglas Gardens; Place; Court; and Avenue

Internal resources

4

 

Heather Gardens; Heather Place; and Forest Gardens

Internal resources

4

 

Heather Drive, Heather Place

Internal resources

4

 

 

Council Ward

Carriageway Resurfacing 2024/25

Quarter

Date Completed

Kirkintilloch East & North Twechar

 

 

 

Waterside Road (Phase 2-overlay)

Internal resources

1

 

Oxford Street

Internal resources

1

 

Kilsyth Road (phase 1)

Internal resources

1

 

Applecross Road

Internal resources

3

 

Braehead Street

Internal resources

3

 

Main Street (phase 1), Twechar

Internal resources

2

 

Main Street (phase 2), Twechar

Internal resources

2

 

 

The under noted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.

Council Ward

Footway Resurfacing 2023/24

Quarter

Date Completed

Milngavie

 

 

 

 

Main Street (Kelvin Timber to Waitrose)

Internal resources

1

 

Mugdock Road

Internal resources

1

 

Station Road

Internal resources

2

 

Prestonfield

Internal resources

2

 

Bearsden North

 

 

 

Milngavie Road

(Westside near Mosshead Road)

Between Kelvin Timber and Waitrose

1

 

Grampian Way

Internal resources

3

 

Bearsden South

 

 

 

Crarae Avenue

Internal resources

1

 

Westfield Drive

Internal resources

1

 

Maxwell Avenue

Internal resources

1

 

Drymen Road

Internal resources

2

 

Killermont Road

Internal resources

TBC

 

Bishopbriggs North & Campsie

 

 

 

Wester Cleddens Road

Internal resources

4

 

Teviot Avenue

Internal resources

TBC

 

Allander Gardens

Internal resources

TBC

 

Lenzie & Kirkintilloch South

 

 

 

Kirkintilloch Road, Lenzie

Internal resources

1 & 2

 

Craigenbay Road

Internal resources

3

 

Laxton Drive

Internal resources

3

 

Bramley Place

Internal resources

3

 

Glenwood Road

Internal resources

3

 

 

The under noted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. 

Council Ward

Carriageway Resurfacing 2024/25

Quarter

Date Completed

Milngavie

 

 

 

 

Clober Road

External resources

TBC

TBC

Blackwood Road

External resources

TBC

TBC

Dougalston Road                     

External resources

TBC

TBC

Connell Crescent                       

External resources

TBC

TBC

Bishopbriggs South

 

 

 

Brora Road & Crescent

External resources

TBC

TBC

Coltpark Avenue                        

External resources

TBC

TBC

Gannochy Drive

External resources

TBC

TBC

Bishopbriggs North & Campsie

 

 

 

Teviot Avenue                            

External resources

TBC

TBC

Lenzie & Kirkintilloch South

 

 

 

Lithgow Avenue

External resource

TBC

TBC

Gallowhill Avenue

External resource

TBC

TBC

The under noted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. 

Council Ward

Footway Resurfacing 2024/25

Quarter

Date Completed

Bishopbriggs South

 

 

 

Coltpark Ave

External resources

TBC

TBC

Bishopbriggs North & Campsie

 

 

 

Meadowburn      

External resources

TBC

TBC

Milngavie

 

 

 

 

Kelvin Road

External resources

TBC

TBC

Crossburn Avenue

External resources

TBC

TBC

The undernoted table shows the locations selected as part of capital carriageway resurfacing 2023 /24. Regrettably, these locations were not progressed as part of the 2024/25 due the identification of coal tar. The works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations require full tendering exercise and framework.  

Council Ward

Carriageway Resurfacing 2024/25

Quarter

Date Completed

Bearsden South

 

 

 

Durness Avenue (phase 1)

External resources

TBC

 

Bearsden North

 

 

 

Lawers Drive

External resources

TBC

 

Bishopbriggs South

 

 

 

Gannochy Drive

External resources

TBC

 

Rannoch Gardens

External resources

TBC

 

Lochy Gardens

External resources

TBC

 

Maree Gardens

External resources

TBC

 

Ness Gardens

External resources

TBC

 

The under noted table shows the locations selected as part of capital footway resurfacing 2023-24. Regrettably, these locations were not progressed as part of the 2023/24 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations are required fully tendering exercise and framework.  

Council Ward

Footway Resurfacing 2023/24

Quarter

Date Completed

Milngavie

 

 

 

South Mains Road

TBC

TBC

 

Lenzie & Kirkintilloch South

 

 

 

Gallowhill Road

TBC

TBC

 

The Service is in the process of renewing the contract to utilise an appointed external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the procurement process the tables within sections 10, 11, 12, and 13 will be updated later in the year.

In summary, the Service is commencing the year with the aspiration to complete the 63 carriageway and 25 footway locations listed, but will add others if additional external resources can be secured during the financial year.