Technical Notes 2024, Issue 172 - Roads & Neighbourhood Services 2024/25 Carriageway and Footway Resurfacing Programme – Quarter 2 Progress Update
- The purpose of the Technical Note is to provide Elected Members with an update on the 2024/25 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme, following the completion of the second quarter of the financial year.
- The Technical Note highlights the work programmes associated with internal and external resources, as well as providing an indication to when this work is programmed to be undertaken.
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
- All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The Service will provide a further quarterly progress update via Technical Notes in January 2025, along with a final update in March 2025.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- It should be noted that the programme and sequence of some locations have been altered from the previously issued Technical Note. This has been due to other works on the network impacting either directly on the planned location or the nominated diversion route. The team have attempted to substitute the locations and re-sequence the programme to ensure that the locations are caught later in the year.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
- The undernoted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward |
Carriageway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Milngavie |
|
|
|
|
Dumgoyne Avenue (Phase 2) |
Internal resources |
1 |
April 2024 |
|
Ellangowan Road |
Internal resources |
2 |
August 2024 |
|
Mugdock Road /Ellangowan Road – RB included |
Internal resources |
2 |
August 2024 |
|
Keystone Quadrant |
Internal resources |
2 |
August 2024 |
|
Drumlin Drive |
Internal resources |
2 |
Postponed |
Positive Coal Tar Test |
Campsie Drive |
Internal resources |
3 |
|
|
McGrigor Road |
Internal resources |
3 |
|
|
Tambowie Crescent |
Internal resources |
3 |
|
|
Allander Road |
Internal resources |
4 |
|
|
Bearsden North |
|
|
|
|
Baljaffray Road (phase 3) |
Internal resources |
1 |
April 2024 |
|
Stockiemuir Road |
Internal resources |
1 |
April 2024 |
|
Russell Drive (phase 1) |
Internal resources |
1 |
June 2024 |
|
Russell Drive (phase 2) |
Internal resources |
1 |
June 2024 |
|
Milngavie Road (Phase 3) – BP Garage to Manse Road |
Internal resources |
3 (subject to completion of Canniesburn Toll Project) |
Scheduled for October 2024 upon completion of Canniesburn Toll Project |
Delayed due to extension of Canniesburn Toll project and reschedule for Q3. |
Bailie Drive |
Internal resources |
3 |
|
|
Campsie Drive |
Internal resources |
4 |
|
|
Bearsden South |
|
|
|
|
Kessington Road (phase 2) |
Internal resources |
1 |
May 2024 |
|
Afton Crescent |
Internal resources |
1 |
May 2024 |
|
Boclair Road (phase1) |
Internal resources |
1 |
June 2024 |
|
Boclair Road (phase2) |
Internal resources |
2 |
July 2024 |
|
Ledi Drive |
Internal resources |
2 |
August 2024 |
Brought forward from 2025-26 programme. |
Methven Avenue + Kenmore Gardens + Ardoch Road |
Internal resources |
3 |
|
|
Second Avenue |
Internal resources |
4 |
|
|
Rannoch Drive (phase 2) |
Internal resources |
4 |
|
|
Albert Drive |
Internal resources |
4 |
|
|
Bishopbriggs North & Campsie |
|
|
|
|
Juniper Drive |
Internal resources |
3 |
|
|
Forth Road/Queensview -Torrance |
Internal resources |
3 |
|
|
Craigmarloch Avenue -Torrance |
Internal resources |
3 |
|
|
Old Balmore Road |
Internal resources |
4 |
|
|
Campsie Road, Lennoxtown
|
Internal resources |
4 |
|
|
Council Ward |
Carriageway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
Bishopbriggs South
|
|
|
|
|
Springfield Square |
Internal resources |
1 |
May 2024 |
|
Fintry Crescent and Tinto Road |
Internal resources |
1 |
June 2024 |
|
Wester Cleddens Road |
Internal resources |
1 |
June 2024 |
|
Crowhill Road (phase 1) |
Internal resources |
2 |
September 2024 |
|
Crowhill Road (phase 2) |
Internal resources |
2 |
September 2024 |
|
Angus Avenue |
Internal resources |
2 |
July 2024 |
Brought forward to July 2024- Switch with Milngavie Road due to conflict with Canniesburn Toll |
Elspeth Gardens |
Internal resources |
3 |
|
|
Lenzie & Kirkintilloch South |
|
|
|
|
Boghead Road (phase 2) |
Internal resources |
2 |
July 2024 |
|
Kirkintilloch Road, Lenzie phase 1 |
Internal resources |
2 |
September 2024 |
|
Southbank Road |
Internal resources |
4 |
|
|
Douglas Gardens; Place; Court; and Avenue |
Internal resources |
4 |
|
|
Heather Gardens; Heather Place; and Forest Gardens |
Internal resources |
4 |
|
|
Heather Drive, Heather Place |
Internal resources |
4 |
|
|
Kirkintilloch East & North Twechar |
|
|
|
|
Waterside Road (Phase 2-overlay) |
Internal resources |
1 |
April 2024 |
|
Oxford Street |
Internal resources |
1 |
May 2024 |
|
Kilsyth Road (phase 1) |
Internal resources |
1 |
June 2024 |
|
Main Street (phase 1), Twechar |
Internal resources |
2 |
Postponed to 2025-26 |
Postponded to next year – Replaced with Ledi Drive - due to conflict with new outdoor center in Twechar |
Main Street (phase 2), Twechar |
Internal resources |
2 |
Postponed to 2025-26 |
Postponded to next year – Replaced with Ledi Dr- due to conflict with new outdoor center in Twechar |
Applecross Road |
Internal resources |
3 |
- |
- |
Braehead Street |
Internal resources |
3 |
- |
- |
- The undernoted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
Council Ward |
Footway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Milngavie |
|
|
|
|
Main Street (Kelvin Timber to Waitrose) |
Internal resources |
1 |
June 2024 |
|
Mugdock Road |
Internal resources |
1 |
June 2024 |
|
Station Road |
Internal resources |
2 |
August 2024 |
|
Prestonfield |
Internal resources |
2 |
August 2024 |
|
Bearsden North |
|
|
|
|
Milngavie Road (Westside near Mosshead Road) |
Between Kelvin Timber and Waitrose |
1 |
Duplicate |
This section is called Main St, and it has already resurfaced in May 2024 |
Grampian Way |
Internal resources |
3 |
|
|
Bearsden South |
|
|
|
|
Crarae Avenue |
Internal resources |
1 |
May 2024 |
|
Westfield Drive |
Internal resources |
1 |
May 2024 |
|
Maxwell Avenue |
Internal resources |
1 |
June 2024 |
|
Drymen Road |
Internal resources |
2 |
Postponed |
Subject to Canniesburn Toll completion |
Killermont Road |
Internal resources |
TBC |
TBC |
Possibly required to carry out with an external resource - cross over from 2023-24- Councilor’s list |
Bishopbriggs North & Campsie |
|
|
|
|
Wester Cleddens Road |
Internal resources |
4 |
|
|
Teviot Avenue |
Internal resources |
TBC |
|
Coal Tar found- External contractor instructed to carry work in 2024-25 |
Allander Gardens |
Internal resources |
TBC |
|
Possible /required to carry out with an external resource- Cross over from 2023-24- Councilor’s list |
Lenzie & Kirkintilloch South |
|
|
|
|
Kirkintilloch Road, Lenzie |
Internal resources |
2 |
July 2024 |
|
Craigenbay Road |
Internal resources |
3 |
|
|
Laxton Drive |
Internal resources |
3 |
|
|
Bramley Place |
Internal resources |
3 |
|
|
Glenwood Road and Place |
Internal resources |
3 |
September 2024 |
|
- The undernoted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor.
Council Ward |
Carriageway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Milngavie |
|
|
|
|
Clober Road |
External resources |
2 |
August 2024 |
External contractor appointed to carry work in 2024-25 |
Blackwood Road |
External resources |
2 |
August 2024 |
External contractor appointed to carry work in 2024-25 |
Dougalston Road |
External resources |
2 |
September 2024 |
External contractor appointed to carry work in 2024-25 |
Connell Crescent |
External resources |
2 |
September 2024 |
External contractor appointed to carry work in 2024-25 |
Bishopbriggs South |
|
|
|
|
Brora Road & Crescent |
External resources |
2 |
|
External contractor appointed to carry work in 2024-25 |
Coltpark Avenue |
External resources |
3 |
|
External contractor appointed to carry work in 2024-25 |
Gannochy Drive |
External resources |
3 |
|
External contractor appointed to carry work in 2024-25 |
Bishopbriggs North & Campsie |
|
|
|
|
Teviot Avenue |
External resources |
3 |
|
External contractor appointed to carry work in 2024-25 |
Lenzie & Kirkintilloch South |
|
|
|
|
Lithgow Avenue |
External resource |
3 |
|
External contractor appointed to carry work in 2024-25 |
Gallowhill Avenue |
External resource |
2 |
August 2024 |
External contractor appointed to carry work in 2024-25 |
- The undernoted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor.
Council Ward |
Footway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Bishopbriggs South |
|
|
|
|
Coltpark Ave |
External resources |
3 |
|
External contractor appointed to carry work in 2024-25 |
Bishopbriggs North & Campsie |
|
|
|
|
Meadowburn |
External resources |
3 |
|
External contractor appointed to carry work in 2024-25 |
- The undernoted table shows the locations selected as part of capital carriageway resurfacing 2023 /24. Regrettably, these locations were not progressed as part of the 2023/24 programme due the identification of coal tar. The works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations require full tendering exercise and framework.
Council Ward |
Carriageway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Bearsden South |
|
|
|
|
Durness Avenue (phase 1) |
External resources |
Completed |
March 2024 |
Full length resurfaced |
Bearsden North |
|
|
|
|
Lawers Drive |
External resources |
TBC |
TBC |
|
Bishopbriggs South |
|
|
|
|
Gannochy Drive |
External resources |
TBC |
TBC |
External contractor appointed to carry work in 2024-25 |
Rannoch Gardens |
External resources |
TBC |
TBC |
External contractor appointed to carry work in 2024-25 |
Lochy Gardens |
External resources |
TBC |
TBC |
External contractor appointed to carry work in 2024-25 |
Maree Gardens |
External resources |
TBC |
TBC |
External contractor appointed to carry work in 2024-25 |
Ness Gardens |
External resources |
TBC |
TBC |
External contractor appointed to carry work in 2024-25 |
- The undernoted table shows the locations selected as part of capital footway resurfacing 2023-24. Regrettably, these locations were not progressed as part of the 2023/24 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations are required fully tendering exercise and framework.
Council Ward |
Footway Resurfacing 2024/25 |
Quarter |
Date Completed |
Comment |
---|---|---|---|---|
Milngavie |
|
|
|
|
South Mains Road |
TBC |
TBC |
TBC |
Investigation required for minor project based on desk top survey – subject to availability of budget |
Kelvin Road |
External resources |
TBC |
TBC |
|
Crossburn Avenue |
External resources |
TBC |
TBC |
|
- The Service has appointed an external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the pre-start meetings, the dates will be confirmed for sections 10, 11, 12, and 13.
- In summary, the Service is commencing the year with the aspiration to complete the 63 carriageway and 25 footway locations listed but will add others if additional external resources can be secured during the financial year.